Post-project evaluation of the paving works executed by the provincial municipality of Puno
Published 2024-12-30
Keywords
- Budget management,
- causes of failure,
- evaluation,
- quality,
- scope
- time ...More
Copyright (c) 2025 Gilmer Maguin Sardón Sanchez

This work is licensed under a Creative Commons Attribution 4.0 International License.
How to Cite
Abstract
The execution of urban road projects in Puno and other Peruvian municipalities faces critical problems in their budget execution, according to reports from the Comptroller General of the Republic. Puno provincial Municipality has experienced many paralyzed projects and variations in investment budget. This research aimed to identify key indicators for assessing efficiency in managing scope, cost, and time in urban road projects executed from 2015 to 2022. In the study, two representative projects to improve urban road service and walkability in the José Antonio Encinas neighborhood and the town center Alto Puno were analyzed. A qualitative-quantitative approach was used, including interviews with relevant public officials, documentary analysis, and ex-ante and ex-post evaluations. The mixed methodology was effective and complete in determining the impact of the projects by comparing the logframe matrix, which revealed significant causes of failure in terms of scope, cost and time. The conclusions reveal the excessive delay in the execution of works by direct administration as the main problem, with a less significant impact on contracted works. The final relationship between scope, cost and time management was 93% and 105%, respectively. In addition, recommendations were proposed based on the methodologies of the Project Management Institute and the International Organization for Standardization to improve project management and reverse the adverse indicators found, attempting to maximize the completion of urban road construction projects in Puno city.
References
- Alianza por la Inversión de Impacto de Mexico. (2020). Guía de Medición de Impacto para la Inversión de Impacto. In Terraética (Ed.), Terraética (Primera ed).
- Barea, J., Martinez, J., & Miquel, A. (2014). El presupuesto como instrumento de gestión pública eficaz . La implantación del presupuesto base cero en la Administración Pública española. Presupuesto y Gasto Público, 11–34.
- Canossa, H. (2022). Gestión de proyectos como estrategia para la evaluación de desempeño del talento humano en la empresa.
- Chamíe, C. (2021). Trabajo de fin de master. Universitat Politecnica de valencia.
- Congreso de la Republica Perú, . (2022). Ley de presupuesto del sector público para el año fiscal 2023.
- DGPI, M. de E. y F. (2012). Pautas Generales para la Evaluación Ex Post de Proyectos de Inversión Pública. In JICA (Ed.), Ministerio de Economía y Finanzas (1ra publi). Agencia de cooperación internacional del Japón. http://www.mef.gob.pe/contenidos/inv_publica/docs/Evaluacion_ExPost/InstrumentosMetodologicos/PAUTAS_GENERALES_EVAL_EX_POST.pdf
- Emam, H., Abdelaal, M., & Farrell, P. (2014). Causas de los retrasos en los proyectos de construcción del CCG : Una revisión crítica. https://doi.org/10.13140/2.1.1211.8086
- Enshassi, A., Ghoul, H. Al, & AlKilani, S. (2018). Exploración de los factores de desarrollo sostenible durante las fases del ciclo de vida de los proyectos de construcción. Revista Ingeniería de Construcción, 33(1), 51–68. https://doi.org/10.4067/s0718-50732018000100051
- Fernández, J. (2014). ISO 21500. Universitat Politécnica de Catalunya.
- Gido, J y Clements, J. (2012). Administración exitosa de proyectos Cengage Learning Editores, S.A. de C.V. (ed.); 5°.
- Gisbert, J y Chaparro, M. (2020). Gastroenterología y Hepatología Reglas y consejos para ser un investigador de éxito. Gastroenterología y Hepatología, 43(9), 540–550. https://doi.org/10.1016/j.gastrohep.2020.03.010
- Gómez, R. (2015). Campaña para lograr proyectos exitosos. Ingenieria y Servicios Tecnológicos SAC (ed.); 1ra ed., Issue July. ISBN N° 978-612-46254-1-1.
- Gonzalez, L. (2014). La evaluación ex-post o de impacto: un reto para la gestión de proyectos de cooperación internacional al desarrollo. In S. . Lankopi (Ed.), Cuadernos de Trabajo Hegoa (Issue 29, p. 47). http://www.ehu.es/ojs/index.php/hegoa/article/view/10792
- INACAL. (2021). Norma Técnica Peruana ISO 19650-2 2021. In D. de N. INACAL (Ed.), organización y digitalización de la información sobre edificios y obras de ingenieria civil BIM (1st ed., Issue Lima 27, p. 55).
- INACAL. (2022). NTP ISO 21500 Gestión de proyectos , programas y portafolios . Contexto y conceptos. In INACAL (Ed.), INACAL (2° Edición, p. 27).
- INACAL, (2022). NTP ISO 21502 Gestión de proyectos , programas y portafolio. Lineamientos para la gestión de proyectos. In INACAL (Ed.), INACAL (1° Edición, Issue Lima 15046, p. 102).
- International Standard Organization. (2015). Norma Internacional ISO 9001. In ISO (Ed.), International Standard Organization (pp. 1–45).
- Islam, M. S., & Trigunarsyah, B. (2017). Retrasos en la construcción en los países en desarrollo : Una revisión. Revista KICEM de Ingenieria de La Construcción y Gestión de Proyectos En Linea, 1–16. https://doi.org/10.6106/JCEPM.2017.3.30.001 Retrasos
- Jefatura del Estado España. (2022). Ley 31/2022, Presupuestos Generales del Estado para el año 2023. BOE-A-2022-22128 (ed.).
- Kelvin, A. (2020). Factors Affecting Quality Control in Building Construction. International Journal of Advances in Scientific Research and Engineering, 5(11), 171–176. https://doi.org/10.31695/IJASRE.2019.33548
- Khaksefidi, M., & Miri, M. (2015). The Role of Project Management Office in the Organization with the Knowledge Approach. Mediterranean Journal of Social Sciences, 6(6), 11–16. https://doi.org/10.5901/mjss.2015.v6n6s6p11
- Kvam, R. (2018). Evaluación del impacto social: Integrar las cuestiones sociales en los proyectos de desarrollo. In BID (Ed.), Banco Interamericano de desarrollo (BID). https://publications.iadb.org/bitstream/handle/11319/8917/Evaluacion-del-impacto-social-web.pdf?sequence=3&isAllowed=y
- Mejia, C., Sánchez, O., Castañeda, K., & Pellicer, E. (2020). Delay causes in road infrastructure projects in developing countries. 2017, 220–234. https://doi.org/10.7764/RDLC.19.2.220
- Mendiola, A., Alvarado, F., Chocano, Z., Cotrado, A., & Aguirre, C. (2011). Factores críticos de éxito en concesiones viales en el Perú. ESAN ediciones (ed.).
- Motoa, G. (2015). Project success assessment , a literature review. Ingenium, September 2015, 11–25. https://doi.org/10.21774/ing.v9i25.584
- ONU. (2023). What is Goal 11 - Sustainable Cities? In Sustainable Development Goald, (pp. 1–2). https://www.un.org/sustainabledevelopment/wp-content/uploads/2023/09/Goal-11_Fast-Facts.pdf
- Othman, I; Shafiq, N y Nuruddin, M. (2017). Quality planning in Construction Project. In IOP Publishing (Ed.), International Conference on Architecture and Civil Engineering (pp. 1–6). https://doi.org/10.1088/1757-899X/291/1/012017
- Parra, J y Luna, J. (2019). Diseño de metodologia lean construction bajo lineamientos gerenciales para laoptimización de resursos en la empresa aedisek. Universidad Catolica de Colombia.
- Project Management Institute. (2017a). Guia de los fundamientos para la Dirección de Proyectos Project Management Institute (ed.); Sexta).
- Project Management Institute. (2017b). Guia de los Fundamentos para la Dirección de Proyectos (PMI (ed.); Sexta edic).
- Riaz, H., Iqbal, K., Khan, A., Ullah, F., Bilal, M., Alqurashi, M., & Alsulami, B. T. (2023). Key factors for implementation of total quality management in construction Sector : A system dynamics approach. Ain Shams Engineering Journal, 14(3), 101903. https://doi.org/10.1016/j.asej.2022.101903
- Romero, A. (2016). Formulacion metodologia lean construccion y PMI para mamposteria. Universidad Militar Nueva Granada, 1–37.
- Saenz, A., Ostos, J., & Bremser, K. (2020). The Influence of the Project Team Efficacy and Organizational Factors on the Success of Mining Project Management. Universidad & Empresa, 22(39), 1–23.
- Santelices, C., Herrera, R., & Muñoz, F. (2019). Problemas en la gestión de calidad e inspección técnica de obra : un estudio aplicado al contexto chileno. 34, 242–251.
- Serrano, E., Herrera, M., Martínez, A., & Díaz, A. (2019). Bases para la Evaluación de Impacto de Políticas Públicas. I. A. de A. Pública (ed.). https://www.juntadeandalucia.es/institutodeadministracionpublica/publico/anexos/evaluacion/Bases_Evaluacion_Impacto.pdf